| 29 May 1959 | | Proposed | £800,000 town house project; proposed start in 1960; 'Aberdeen Town Council authorised to undertake loan facilities' and formal application per Builder p978 |
| September 1959 | | Proposed | 'hope to start in September or October their £850,000 scheme...[for] municipal offices...The Secretary of State for Scotland was prepared to sanction the borrowing of up to £385,000 to meet the cost of the first phase' per Builder p978 |
| 9 October 1959 | | Proposed | work to begin; construction in two sections: the first stage - an L-shaped block w/ 200 ft. frontage and a 200 ft. wing (1/2 of building) and - the second stage - similar but tbd based on planning and demolition works; work also includes widening of Broad street; est. cost £700,000 (£325,000 for first stage) per Builder p415 |
| 16 October 1959 | | Scheme accepted | £10K to be spent on sculpture for scheme per Builder p459 |